BAE Automated Systems (A): Denver International Airport Baggage-Handling System

View Paper
ESSAY DETAILS Words: 1871
Pages: 7
(approximately 235 words/page)

Essay Database > Business & Economy
Critical Factors *A change in the project specifications after the freeze date was agreed up on in the contract. These changes created a domino effect of problems. This was in violation of the contract with BAE which stated there would be a number of freeze dates for mechanical design, software design, and permanent power. *A lack of efficient and effective communication between the city, project management team, and consultants. This manifests itself in basic issues …

showed first 75 words of 1871 total
Sign up for EssayTask and enjoy a huge collection of student essays, term papers and research papers. Improve your grade with our unique database!
showed last 75 words of 1871 total
…using it while the issues are being worked out from the state of the art baggage handling system can allow the airport to open sooner and allow the necessary revenues to begin to pay back the bonds. This alternative will allow BAE to properly diagnose and fix all of the issues that the system is currently experiencing. BAE originally told the City of Denver that a project this size should be completed in about 2.5 years.